Products
Industries
Quick installation in challenging geographies at Bornhausen landfill
Overview
Bornhausen Landfill is in Seesen, a town in the district of Goslar, in Lower Saxony, Germany.
Solmax installed 150,000 m² (1.6 million ft²) of geosynthetics as part Kreiswirtschaftsbetriebe KWB Goslar’s groundwater protection landfill project. The landfill is Class II covering an area of 7.5 hectares with a gradient of up to 1:3. This geosynthetic layer helps to protect the surrounding environment. Waterproofing work began in March 2021 and was completed in June 2022.
Challenge
The landfill is situated in the Harz Mountains, which experiences unpredictable and sudden rain showers that made the installation difficult. The geography of the area is also challenging because of long, steep slopes up to 120 m (394 ft) long. The installation team needed to work efficiently to make sure the geomembranes were not installed during rain.
Despite the unfavorable weather conditions and geometry, a total of 150,000 m² (1.6 million ft²) of geosynthetics were laid on the construction site in 2021.
Solution
Solmax supplied and installed GSE® HD with BAM-certification, 2,5 mm (1 mil) and FABRINET® with BAM-certification, which provides increased durability for filtration and drainage, and is suitable for a variety of field conditions and thickness requirements. The installation team consisted of one senior welding technician and two welding technicians plus additional helpers.
BORNHAUSEN LANDFILL, GERMANY
BORNHAUSEN LANDFILL, GERMANY
Explore more case studies
View allSilt trap dewatering for Kestrel Coal Mine
Kestrel Coal Resources restored silt trap capacity by dredging and dewatering 40,000m³ of silt using GEOTUBE units. The project preserved coal fines for sale.
Innovative application of new GEOTUBE technology incorporating moisture draining yarns for enhanced dewatering performance of gold tailings slurry
A gold mine in Victoria, Australia, used Solmax GEOTUBE units with moisture-absorbing wicking yarns to improve water release, efficiently managing increased slurry waste in its limited-capacity tailings storage.
Soft-soil consolidation improvements ensure new housing development launches on time
Solmax provided a custom GSE HD geomembrane solution for the Summarecon Housing Estate in Bandung, enabling full soil consolidation in four months and ensuring the project launched on time.