Stabilization and construction of a new arterial roadway in using MIRAFI
Overview:
The City of Eagle Mountain, Utah experienced significant population growth from 2010 to 2021 leading the City to develop a comprehensive transportation plan to combat potential congestion. Part of this plan included a new roadway running adjacent to a new middle and high school. This roadway would be used to carry heavy loads during the construction of the new schools and serve as an arterial roadway for the Eagle Mountain community.
The project engineer needed to stabilize the fine-grained subgrade soils, which exhibited collapse potential as per laboratory tests, and minimize the base aggregate requirement for the roadway. The goal was to optimize the base layer for a heavily trafficked roadway leading to Eagle Mountain City and the upcoming middle and high schools along this route.
Challenge
Using Solmax’s design software, the project engineer designed the roadway cross-section with MIRAFI® RS580i. This allowed for the elimination of 5 in (12.7 cm) of granular borrow, offering a cost-effective solution.
For this new roadway, the contractor initially cleared the area to subgrade level. The top 12 in (30.5 cm) of fine-grained subgrade soils were reworked by scarifying and recompacting them to a minimum dry density of 95 percent according to ASTM D-1557 (modified proctor) standards, with moisture near optimum. Following this, MIRAFI RS580i was installed, and the new pavement section was built. The installation process was smooth and exceeded expectations.
Solution
The roadway outperformed expectations. Both the contractor and the City were satisfied with the installation and the performance of the materials used. The engineer was equally pleased with the installation process and the material's performance so far, as well as the simplicity of the design process.
The fine-grained subgrade soils are scarified and recompacted to ensure a uniform and stable foundation
Following the installation of MIRAFI RS580i, construction of the new pavement section begins
The completed roadway, designed with Solmax’s software, shows excellent performance
Explore more case studies
View allSilt trap dewatering for Kestrel Coal Mine
Kestrel Coal Resources restored silt trap capacity by dredging and dewatering 40,000m³ of silt using GEOTUBE units. The project preserved coal fines for sale.
Soft-soil consolidation improvements ensure new housing development launches on time
Solmax provided a custom GSE HD geomembrane solution for the Summarecon Housing Estate in Bandung, enabling full soil consolidation in four months and ensuring the project launched on time.
Innovative application of new GEOTUBE technology incorporating moisture draining yarns for enhanced dewatering performance of gold tailings slurry
A gold mine in Victoria, Australia, used Solmax GEOTUBE units with moisture-absorbing wicking yarns to improve water release, efficiently managing increased slurry waste in its limited-capacity tailings storage.