Channel stabilization protects against floods
Overview
Middle Logan Creek runs through Randolph, Nebraska from west to east, placing much of the town in a federally designated floodplain. Due to the flooding, residents in Randolph are required to carry expensive flood insurance. Permits for the construction of new buildings and renovations of existing ones have been placed on hold because of the location. The area has been flooded 14 times in the past 100 years, with the last major flood occurring in 2019. The unpredictable nature of the flooding has caused a severe impact on the town.
Challenge
To remove most of the town from the floodplain, the U.S. Army Corps of Engineers widened a 2.4 km (1.5 miles) segment of Middle Logan Creek. After the channel was extended, PROPEX® Armormax® was installed on the slide slopes to stabilize vegetation.
Solution
The end goal of the project is to carry water from future 100-year floods through the city in the channel and eliminate flooding in Randolph. The project was very successful, vegetation for the widened channel is protected and stabilized with PROPEX Armormax, therefore increasing resiliency.
Middle Logan Creek, Nebraska Channel stabilization PROPEX Armormax
Middle Logan Creek, Nebraska Channel stabilization PROPEX Armormax
Explore more case studies
View allSoft-soil consolidation improvements ensure new housing development launches on time
Solmax provided a custom GSE HD geomembrane solution for the Summarecon Housing Estate in Bandung, enabling full soil consolidation in four months and ensuring the project launched on time.
Innovative application of new GEOTUBE technology incorporating moisture draining yarns for enhanced dewatering performance of gold tailings slurry
A gold mine in Victoria, Australia, used Solmax GEOTUBE units with moisture-absorbing wicking yarns to improve water release, efficiently managing increased slurry waste in its limited-capacity tailings storage.
Silt trap dewatering for Kestrel Coal Mine
Kestrel Coal Resources restored silt trap capacity by dredging and dewatering 40,000m³ of silt using GEOTUBE units. The project preserved coal fines for sale.