
Products
Industries
Rebuilding U.S. Route 441 and enhancing flood resilience with MIRAFI
Overview
On the south side of Gainesville, Florida, U.S. Route 441 runs through Paynes Prairie Preserve State Park. This 2.5 mi (4 km) section of roadway is surrounded by swamp land, and standing water is common. The groundwater table is very high, and this portion of the roadway commonly floods after large storm events. Due to the rapid rise and fall of groundwater, fines and organics have mixed into the roadway base, resulting in ongoing maintenance issues. In 2017, this section of U.S. Route 441 was flooded during Hurricane Irma, leaving severe damage to the roadway. The Florida Department of Transportation (FDOT) sought a solution to reconstruct the roadway that would provide long-term performance.
Challenge
Environmental & Geotechnical Specialists (EGS) performed the geotechnical design and recommendations for the roadway reconstruction. Borings indicated silty sands with organics and groundwater were between 2 and 7 ft (0.6 and 2.13 m) below the roadway surface. Additionally, the high fine content of the subgrade made stabilization extremely challenging.
Solution
The design for the reconstructed roadway involved removing the existing asphalt and roadway base and placing 105,000 yd² (87,793 m²) of MIRAFI® RS580i directly on the exposed subgrade. No other subgrade stabilization methods were used. After the placement of the MIRAFI RS580i, 11 inches (28 cm) of graded aggregate base was placed and compacted. The final step in the design involved placing the asphalt.
The reconstruction was completed in December 2021. Since reopening, the highway has endured multiple hurricanes and flood events. The high flow rate of MIRAFI RS580i and its ability to provide separation has prevented fines and organics from contaminating the roadway base. The roadway continues to perform well without requiring maintenance or repair. To date, this is the largest FDOT installation of the RSi material.


Explore more case studies
View allMIRAFI geotextiles prevent subgrade failure and reduce track downtime
Canadian Pacific Railway (CP) identified track settlement issues and partnered with Solmax and Clifton Associates to implement a geosynthetic solution, reducing ballast use by 43% and completing repairs on a 72 ft section in under seven hours.

MSE walls with MIRAGRID XT for rail expansion
GO Transit used hybrid MSE walls with MIRAGRID XT geogrids to stabilize embankments on Lakeshore West Line, ensuring stability under space and load constraints.
Stabilizing soft clay soils and shallow utilities during the reconstruction of Main Street
Main Street in Palisade, CO, was reconstructed using geosynthetics to address soft soils and shallow utilities, reducing excavation and aggregate use.