Asia's longest dewatering GEOTUBE in Indonesia's Kalimantan region
Overview
The increasing demand for large-scale GEOTUBE® dewatering units capable of handling vast quantities of mine waste sediments and slurries has driven geosynthetics to strive for innovation and engineering excellence. Mine owners and plant operators require more efficient and productive solutions, tailored to their specific site and operational needs.
Challenge
The mine site faced the challenge of dewatering high volumes of slurry from sediment ponds that had reached their maximum capacity. Limited land space prevented the construction of additional ponds, and operational water demand necessitated the circulation of sediment-free water back into the process. The proposed solution had to efficiently dewater exceptionally large volumes of slurry within a limited time frame, while also being cost-effective and functional in an extremely remote location.
Solution
Drawing on their extensive experience in remote mine sites worldwide, Solmax's dewatering engineers quickly realized that standard sized GEOTUBE units were insufficient for this project. The only viable option was to manufacture GEOTUBE units of at least 100 m (328 ft) in length to meet the dewatering targets and fit within the constrained laydown pad size.
The design of the units allowed for efficient pumping of the required volumes and immediate circulation of discharged water back into the process. Calculations showed that using these large tubes significantly reduced operational costs compared to employing a larger number of smaller GEOTUBE units.
For this project, a GEOTUBE unit with a circumference of 36.6 m (120 feet) and a length of 101 m (331 ft) was chosen. Six units were needed to process the 160,000 m³ (209,470 yd³) of slurry pumped at a rate of 550 m³ (720 yd³) per hour, 24 hours a day, resulting in 20,000 m³ (26,156 yd³) of dry cake.
The manufacturing of such large GEOTUBE units presented another challenge, which was overcome through innovative fabric production and tube assembly techniques that no other company can match. The GEOTUBE units were also packaged and transported to the site in a manner that facilitated easy handling and deployment by unskilled labor. This record-breaking operation paves the way for the delivery of supersized GEOTUBE units capable of dewatering extremely large volumes of mine and industrial slurries in the future.
Result
This project holds the distinction of being Asia's longest GEOTUBE dewatering project. It has generated valuable knowledge about the economics of large-scale GEOTUBE dewatering, applicable to other high-volume mines and industrial slurry dewatering challenges.
Kalimantan region Indonesia GEOTUBE
Kalimantan region Indonesia GEOTUBE
Kalimantan region Indonesia GEOTUBE
Kalimantan region Indonesia GEOTUBE
Kalimantan region Indonesia GEOTUBE
Kalimantan region Indonesia GEOTUBE
Kalimantan region Indonesia GEOTUBE
Explore more case studies
View allSilt trap dewatering for Kestrel Coal Mine
Kestrel Coal Resources restored silt trap capacity by dredging and dewatering 40,000m³ of silt using GEOTUBE units. The project preserved coal fines for sale.
Soft-soil consolidation improvements ensure new housing development launches on time
Solmax provided a custom GSE HD geomembrane solution for the Summarecon Housing Estate in Bandung, enabling full soil consolidation in four months and ensuring the project launched on time.
Innovative application of new GEOTUBE technology incorporating moisture draining yarns for enhanced dewatering performance of gold tailings slurry
A gold mine in Victoria, Australia, used Solmax GEOTUBE units with moisture-absorbing wicking yarns to improve water release, efficiently managing increased slurry waste in its limited-capacity tailings storage.