
Products
Industries
Slope stabilization and moisture control on Old Pacific Highway
Overview
The Old Pacific Highway is the original freeway section which runs parallel to the current Interstate 5. Nestled on the hillside, a global stability issue created a slide of the natural slope and a large crack in the pavement section.
Challenge
This project was treated like a deep patch repair and initial repair strategies conceptually included the removal and disposal of the existing asphalt roadway and aggregate subbase, over-excavation of native subsurface soils to a depth anticipated between 2 and 6 ft, the installation of four layers of geogrid in combination with Crushed Surfacing Base Course (CSBC), and Hot Mix Asphalt (HMA) surfacing. However, during geotechnical exploration, an area of high saturation was noted at the bottom of the slip zone, approximately 6 ft down from the existing road surface. The project team was worried that if they repaired this section without addressing the moisture issue, it would not be long until the same section of roadway required additional repair.
Solution
The MIRAFI® H2Ri system was selected because it provides a long-term defense against saturated soils under the steepened slope. The main goal was to prevent accumulation of moisture below the slope repair, where there is a known slip plane which has been problematic. The project team acknowledged that the saturated zone would be a continuing problem. The MIRAGRID® Miramesh facing met aesthetic requirements and long-term performance. The revised solution did not deviate much from the anticipated repair plan and allowed the project team to move forward without over excavation and increased reinforcement lengths.

The MIRAFI H2Ri system was installed to prevent moisture accumulation beneath the slope repair, addressing the known slip plane and ensuring long-term stability

Four layers of geogrid were combined with CSBC and HMA surfacing, reinforcing the roadway while mitigating soil saturation at the bottom of the slip zone

The revised repair plan incorporated the MIRAGRID Miramesh facing to meet aesthetic and performance requirements, allowing the project team to proceed without over-excavation or extended reinforcement lengths
Explore more case studies
View allReinforcing stability in harsh weather with MIRAFI RS580i
Approximately 6 acres of parking lots at a commercial office complex in Maine were rebuilt using MIRAFI RS580i to stabilize the base course, minimize excavation, and withstand extreme freeze-thaw conditions.
MSE pile-supported embankment with MIRAGRID 8X
The I-15 CORE Project in Provo, Utah, used a pile-supported embankment with MIRAGRID 8XT geogrid to stabilize soft soils and meet seismic and space constraints.
Stabilizing Red Hill landfill cap with PROPEX Armormax
Red Hill Landfill in Northern California stabilized a failed slope using the PROPEX Armormax system with PROPEX Pyramat 75 HPTRM and B3 anchors, enhancing safety and erosion control.